[Free] 2019(Oct) EnsurePass CompTIA PK0-004 Dumps with VCE and PDF 1-10

Get Full Version of the Exam
http://www.EnsurePass.com/PK0-004.html

Question No.1

Which of the following risk strategies is represented by the purchase of insurance?

  1. Mitigate

  2. Accept

  3. Transfer

  4. Avoid

Correct Answer: C

Explanation:

quot;Transfer: Moving the liability for the risk to a third party by purchasing insurance, performance bonds, and so onquot;

Question No.2

A project manager is releasing resources and archiving documents. Which of the following phases is the project MOST likely in?

  1. Initiation

  2. Planning

  3. Monitor and control

  4. Closing

Correct Answer: D

Question No.3

Which of the following are characteristics of a project? (Choose two.)

  1. Ongoing

  2. Temporary

  3. Start and finish

  4. Achieving a goal

  5. Consisting of milestones

  6. Restricting the budget

Correct Answer: BC

Explanation:

Kim Heldman, CompTIA Project Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 27

Question No.4

A project manager has identified a minor skills gap in the operational team that will end up supporting the project solution. Which of the following is the BEST risk mitigation strategy that the project manager should use?

  1. Organize adequate training and have one of the operational staff as part of the project team.

  2. Raise a risk in the risk register, identify the likelihood and the consequence of the risk occurring.

  3. Have the project adequately document the solution and ensure a transition is in place.

  4. Escalate this as an issue to the project control board and ensure that there is adequate discussion.

Correct Answer: A

Question No.5

A software upgrade project has been postponed because it may impact a critical business system. Which of the following strategies has been applied?

  1. Accept risk

  2. Mitigate risk

  3. Avoid risk

  4. Exploit risk

Correct Answer: C

Question No.6

The key stakeholders have reported the project pace as being slow. The project sponsor would like to cancel the project if it cannot be completed before the end of the year. The project is scheduled to be completed three months after the requested date. To alter the pace of the project, which of the following should the project manager do FIRST?

  1. Give approval for the change requested by the project sponsor.

  2. Deny the request from the project sponsor.

  3. Document the change request from the project sponsor.

  4. Ask the project sponsor to change the request.

Correct Answer: C

Question No.7

During the initiation phase, a project manager has asked for a document containing the high-level objectives and goals for a project. Which of the following documents would contain these items?

  1. Business case

  2. Requirements document

  3. Project timeline

  4. Task plan

Correct Answer: B

Explanation:

Kim Heldman, CompTIA Project Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 138

Question No.8

A quality auditor finds suspicious code during a software test. For which of the following could this be a trigger?

  1. Incident response

  2. Quality control

  3. Resource changes

  4. Business continuity response

Correct Answer: A

Question No.9

Which of the following roles has approval authority for project funding?

  1. Champion

  2. Chief Financial Officer (CFO)

  3. Project Management Office (PMO)

  4. Sponsor

Correct Answer: D

Question No.10

Which of the following job roles is primarily tasked with communicating the project timeline changes?

  1. Project scheduler

  2. Project manager

  3. Project sponsor

  4. Project coordinator

Correct Answer: B

Explanation:

Kim Heldman, CompTIA Project Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 93

Get Full Version of the Exam
PK0-004 Dumps
PK0-004 VCE and PDF

Leave a Reply

Your email address will not be published. Required fields are marked *